West Contra Costa Transportation Commission

Richmond Parkway Transit Plan — Appendix F: Cost estimates

What the concept would cost to build and to run.

Appendix · Final · 2025 · about 10 min to read

What the concept would cost to build and to run.

Current — In force. This is the version to rely on. The adopted final version.

Original PDF

Appendix F:

Priority Strategy

Cost Estimates

Appendix F: Priority Strategy Cost Estimates |

RICHMOND PARKWAY TRANSPORTATION PLAN

Page intentionally left blank.

STRATEGY PH-2 - TREE PLANTING AND LANDSCAPING (NON-BIORETENTION)
UNITUNIT COSTQUANTITY PER 100 LFCOST PER 100 LFCOST PER MILE
Clear and GrubbingSF$ 31600$ 4 ,800$ 2 53,440
IrrigationLS$ 1 0,0001$ 1 0,000$ 5 28,000
Shrub Planting - 5 Gal.EA$ 5 028$ 1 ,400$ 7 3,920
Tree Planting - 15 Gal.EA$ 2 5025$ 6 ,250$ 3 30,000
MulchSF$ 11600$ 1 ,600$ 8 4,480
GRAND TOTAL
2024 CONSTRUCTION COST$ 1,270,000
2030 TOTAL COST WITH GENERAL COST FACTORS (3)$ 2,900,000
STRATEGY PH-2 - BIORETENTION WITH LANDSCAPING
DESCRIPTION QUANTITCOST/SFCOST/LF COST/MILE
BIORETENTION BASIN (4')4$180$720$3,258,514
2024 CONSTRUCTION COST$3,258,514
2030 TOTAL COST WITH GENERAL COST FACTORS (3)$ 7,430,000

Assumptions

2. Topsoil not included.

1. Labor is included in the cost of plant materials.

4. Assume all plants will be hand watered within an establishment period of one year with

maintenance and monitoring by others.

3. Assume approximately 16 ft planting width.

5. Assume that after a one year establishment period, plants will be drought tolerant native plants

with no irrigation requirements.

Strategy PH-2

Appendix F: Priority Strategy Cost Estimates |

STRATEGY S-2 - SPEED FEEDBACK AND LIMIT SIGNS
QUANTITYUNIT COSTTOTAL COST
Speed Feedback Signs4$5,000$20,000
Speed Limit Signs6$700$4,200
GRAND TOTAL
2024 CONSTRUCTION COST$ 24,200
2030 TOTAL COST WITH GENERAL COST FACTORS (3)$ 55,117

RICHMOND PARKWAY TRANSPORTATION PLAN

Location I80 WB ramp/Blume Dr/Richmond Parkway I580 WB ramps & Castro Street I80 HOV off-ramp & Richmond Pkwy I80 EB ramp & Richmond Pkwy/Fitzgerald Dr Mills Street & Castro Street Castro Street & Richmond Lane Hensley Street & Castro Street W Ohio Avenue/Garrard Street & Richmond Pa MacDonald Avenue & Richmond Parkway W Barrett Avenue & Richmond Parkway Hensley Street & Richmond Parkway Gertrude Avenue & Richmond Parkway Pittsburgh Avenue & Richmond Parkway Parr Boulevard & Richmond Parkway Goodrick Ave & Richmond Parkway Hilltop Drive & Richmond Parkway Atlas Rd & Richmond Parkway San Pablo Ave & Richmond Parkway Lakeside Drive & Richmond Parkway Bella Vista & Richmond Parkway Canal Blvd & I580 WB ramps Canal Blvd & I580 EB ramps Castro St/Standard Ave & Chevron Wy I580 EB TOTAL Proposed High Vis Crosswalks (per Crossing) Proposed Directional Ramps (per Each) Proposed PPB (per Intersection) Proposed Reflective Backplates (per Proposed Bike Video Detection (per Proposed Ped Scale Lighting (per Intersection) Proposed Ped Countdown Signal (per $47,374 $109,324 $39,858 $0 $113,879 $207,259 $0 $47,374 $127,544 $19,929 $0 $113,879 $207,259 $0 $0 $0 $0 $14,576 $0 $0 $13,665 $0 $0 $0 $0 $0 $207,259 $13,665 $47,374 $145,765 $39,858 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $39,858 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $39,858 $14,576 $113,879 $207,259 $13,665 $23,687 $127,544 $19,929 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $19,929 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $39,858 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $39,858 $14,576 $0 $207,259 $13,665 $47,374 $145,765 $19,929 $14,576 $113,879 $207,259 $0 $47,374 $109,324 $0 $14,576 $113,879 $207,259 $0 $47,374 $127,544 $19,929 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $19,929 $14,576 $0 $207,259 $0 $47,374 $145,765 $19,929 $14,576 $113,879 $207,259 $13,665 $47,374 $145,765 $19,929 $14,576 $0 $207,259 $13,665 $47,374 $182,206 $19,929 $14,576 $113,879 $207,259 $13,665 $35,530 $109,324 $19,929 $14,576 $0 $207,259 $0 $35,530 $109,324 $19,929 $14,576 $0 $207,259 $13,665 $0 $163,985 $19,929 $0 $113,879 $207,259 $6,833 $0 $163,985 $0 $14,576 $113,879 $207,259 $13,665 $11,843 $36,441 $19,929 $0 $113,879 $207,259 $0 Assumptions

  1. See General Cost Factors below.

General Cost Factors Mobilization, Demobilization, Environmental Protection, Traffic Control 1.20 Engineering, Design, and Construction Management 1.20 Inflation 1.22 Contingency 1.30 TOTAL - Combined Cost Factor 2.28

  1. Speed Feedback Signs will be spaced about 5 miles apart and speed limit signs will be spaced about 3 miles apart.

Strategy S-1

Strategy S-2

Original PDF, page 5

Straighten Crosswalks (per Crosswalk) Tighten Curb Radii (per corner) Raised Crosswalks (per Each) Porkchop Island with Raised Crosswalk Major Bike Intersection Improvements (per Minor Bike Intersection Improvements (per Enforce Right- Turn Only Lane (per NRTOR (per Intersect ion) Protected Right- Turn Phase (per Intersection) Median Refuge Islands (per Intersection) TOTAL $0 $0 $49,218 $0 $0 $0 $0 $0 $77,438 $84,270 $728,619 $0 $271,031 $49,218 $91,354 $0 $0 $0 $0 $0 $84,270 $1,011,858 $0 $0 $0 $0 $0 $0 $0 $9,110 $0 $0 $37,352 $0 $0 $49,218 $0 $0 $0 $0 $0 $77,438 $0 $347,581 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $582,376 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $582,376 $0 $271,031 $0 $182,707 $0 $120,028 $0 $9,110 $0 $84,270 $1,249,523 $0 $0 $0 $0 $0 $0 $0 $9,110 $77,438 $0 $607,087 $0 $135,516 $0 $0 $0 $0 $0 $0 $77,438 $0 $775,400 $0 $0 $0 $182,707 $0 $0 $0 $0 $77,438 $0 $842,520 $0 $542,063 $0 $0 $0 $0 $0 $0 $77,438 $0 $1,087,997 $0 $0 $0 $365,414 $0 $0 $120,711 $0 $77,438 $84,270 $1,196,615 $0 $0 $0 $0 $0 $0 $120,711 $9,110 $0 $84,270 $706,504 $0 $0 $0 $365,414 $0 $0 $120,711 $0 $0 $84,270 $1,114,622 $0 $0 $0 $0 $2,751,765 $0 $0 $0 $0 $0 $3,186,668 $0 $0 $0 $0 $2,751,765 $0 $0 $0 $77,438 $0 $3,391,650 $0 $0 $0 $365,414 $0 $0 $0 $0 $77,438 $0 $891,420 $0 $0 $0 $0 $2,751,765 $0 $0 $0 $77,438 $0 $3,428,091 $0 $271,031 $0 $0 $0 $0 $0 $0 $77,438 $84,270 $819,357 $0 $271,031 $0 $0 $0 $0 $0 $0 $0 $84,270 $755,585 $0 $271,031 $0 $0 $0 $0 $0 $0 $0 $0 $782,916 $0 $271,031 $0 $0 $0 $0 $0 $0 $0 $0 $784,397 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $389,351 $25,299,864 SUBTOTALS

Appendix F: Priority Strategy Cost Estimates |

Strategy S-1 (cont.)

Original PDF, page 6

STRATEGY WB-1- ROADWAY TYPICAL SECTION COSTS
$1,157 $134$6,110,016 $710,028
COST ($/TON) $170 $100
TS
ION COMPONENDESCRIPTION QUANTITY COST/SF SIDEWALK (LF) 12 $30 CONCRETE WITH GREEN ELEMENTS BIORETENTION BASIN (4') 4 $180 PLANTER STRIP (4') 4 $25 CENTER PLANTER/MEDIAN 14 $25COST/LF COST/MILE
$360 $720 $100 $350$1,900,800 $3,258,514 $603,429 $1,848,000
ECT
SDESCRIPTION QUANTITY COST COST/LF COST/MILE RUMBLE STRIPS 4 $2 PER LF $8 $42,240 LANE STRIPING 6 $1 PER LF $6 $31,680 OTHER ASSUMED COSTS SD INLET RELOCATIONS 1 $10,000 PER EACH $15 $80,000 SD CXN TO EXISTING (15" RCP) 6 $530 PER LF $5 $25,440 HARDSCAPE BUFFER (2', AT EXISTING 2 $100 PER LF $200 $1,056,000 BRIDGE)
$8 $6 $15 $5 $200$42,240 $31,680 $80,000 $25,440 $1,056,000
TOTAL, 2024 CONSTRUCTION COST NEW SIDEWALKS TOTAL, WITH GENERAL COST FACTORS*, 2030$366 $834$1,932,480 $4,401,367
TOTAL, 2024 CONSTRUCTION COST NEW BIKEWAYS WITH PLANTERS TOTAL, WITH GENERAL COST FACTORS*, 2030$988 $2,251$4,751,331 $10,821,509
CASESONE SIDE FULL SECTION: TWO NEW LANES, BIKE LANE TOTAL, 2024 CONSTRUCTION COST WITH PLANTER, AND SIDEWALK TOTAL, WITH GENERAL COST FACTORS*, 2030$1,253 $2,853$6,381,073 $14,533,368
SPECIAL CASE: EXISTING BRIDGE. HARDSCAPE SHARED TOTAL, 2024 CONSTRUCTION COST USE PATH BUFFER AND RESTRIPE TOTAL, WITH GENERAL COST FACTORS*, 2030$206 $469$1,087,680 $2,477,272
FULL SECTION - ALL NEW CONSTRUCTION INCLUDING TOTAL, 2024 CONSTRUCTION COST MEDIAN TOTAL, WITH GENERAL COST FACTORS*, 2030$2,856 $6,504$14,610,147 $33,275,694
TOTAL, WITH GENERAL COST FACTORS*, 2030 RANGE: $3M - $33M PER MILE (Median of $18M)

RICHMOND PARKWAY TRANSPORTATION PLAN

1.20 Mobilization, Demobilization, Environmental Protection, Traffic Control 1.20 Engineering, Design, and Construction Management 1.22 Inflation 1.30 Contingency 2.28 TOTAL - Combined Cost Factor C3 Estimates per mile 75 LF 396000 SF 15840 SF 4526 LF 6034 LF Assumptions Does not take into account ROW acquisitions or agency coordination.

Existing mulitiuse paths will remain and not be replaced. LF of 4' nominal width of bioretention planter (3.5') Remaining planter, non bioretention basin Total Impervious of Cross Section Total Impervious Area 4% = Required Area of Treatment

  • General Cost Factors

Strategy WB-1

Original PDF, page 7

BAY TRAIL REALIGNMENT (GERTRUDE TO HENSLEY)
UNITQUANTITYUNIT COSTTOTAL COST
GERTRUDE AVE INTERSECTION IMPROVEMENTS
DIRECTIONAL CURB RAMPSEA2$ 8,000$ 16,000
SIDEWALKSF200$ 30$ 6,000
HIGH VIS CROSSWALKLF100$ 40$ 4,000
BOLLARDSEA2$ 2,000$ 4,000
TRAFFIC SIGNAL RELOCATIONEA1$ 5 0,000$ 50,000
TRAFFIC SIGNAL PED UPGRADESLS1$ 2 7,000$ 27,000
UTILITY COORDINATIONLS1$ 5 0,000$ 50,000
TRAIL
ASPHALT FOR TRAILTONS690$ 1 70$ 1 17,300
AGGREGATE BASE FOR TRAILTONS2590$ 1 00$ 2 59,000
PLANTER/FLOW THROUGHSF15400$ 25$ 3 85,000
BIOSWALESF1400$ 1 00$ 1 40,000
WAYFINDING SIGNSEA10$ 1,000$ 10,000
PATH LIGHTINGLF2800$ 1 25$ 3 50,000
HENSLEY ST INTERSECTION IMPROVEMENTS
DIRECTIONAL CURB RAMPSEA2$ 8,000$ 16,000
MEDIAN REFUGE ISLANDEA1$ 1 5,000$ 15,000
SIDEWALKSF200$ 30$ 6,000
HIGH VIS CROSSWALKLF100$ 40$ 4,000
BOLLARDSEA2$ 2,000$ 4,000
TRAFFIC SIGNAL PED UPGRADESLS1$ 2 7,000$ 27,000
TOTAL, 2024 CONSTRUCTION COST$ 1,490,300
TOTAL, WITH GENERAL COST FACTORS*, 2030$ 3,394,269
WIDEN PATH TO 12' (PARR TO GERTRUDE)
UNITQUANTITYUNIT COSTTOTAL COST
ASPHALT FOR TRAILTONS1210$ 1 70$ 2 05,700
AGGREGATE BASE FOR TRAILTONS4530$ 1 00$ 4 53,000
PLANTERSF29400$ 25$ 7 35,000
PATH LIGHTINGLF4900$ 1 25$ 6 12,500
TOTAL, 2024 CONSTRUCTION COST$ 2,006,200
TOTAL, WITH GENERAL COST FACTORS*, 2030$ 4,569,269
TOTAL FOR REALIGNMENT AND WIDENING $ 7,963,538
  • General Cost Factors

Mobilization, Demobilization, Environmental Protection, Traffic Control 1.20 Engineering, Design, and Construction Management 1.20 Inflation 1.22 Contingency 1.30 TOTAL - Combined Cost Factor 2.28

Assumptions

1. Pavement section is 3"

hot mix asphalt over 12"

aggregate base.

2. Trail is 12' wide and

planter is 6' wide and does

not require new curb.

3. Trail length is

approximately 2,800 feet.

4. No right of way

acquisition.

5. Utility coordination is

with West County Waste

Water (facility on SW corner

of Gertrude/Richmond

Pkwy) and others.

6. Path lighting does not

necessarily illuminate the

roadway.

Assumptions

1. Does not take into

account ROW acquisitions

or agency coordination.

2. No work will be

performed on bridges.

3. Existing mulitiuse paths

will remain and not be

replaced.

4. C.3 requirements not

applicable (<1 contiguous

acre).

Strategy WB-1 (cont.)

Appendix F: Priority Strategy Cost Estimates |

STRATEGY WB-2 - WILDCAT CREEK TRAIL CROSSING
UNITQUANTITYUNIT COSTTOTAL COST
NEW PAVEMENT - ROAD (1)
MILLING (3" DEPTH)SY510$ 10$ 5,100
HOT MIX ASPHALTTON130$ 170$ 22,100
AGGREGATE BASETON80$ 100$ 8,000
NEW PAVEMENT - TRAIL CONNECTIONS (2)
GRADINGCY320$ 80$ 25,600
HOT MIX ASPHALTTON60$ 170$ 10,200
AGGREGATE BASETON230$ 100$ 23,000
CONCRETE
CONCRETE (SIDEWALKS, CURB & GUTTER, CURB RAMPS, MEDIANS/PED ISLANDS, MEDIAN NOSES)SF1700$ 30$ 51,000
CURB RAMPS (EACH, EXTRA COSTS, FORMWORK, DWS)EA5$ 5,000$ 25,000
ELECTRIC
NEW SIGNAL (INCL. TRAFFIC SIGNALS, PED LIGHTED CROSS/STOP SIGNAGE, VIDEO DETECTION, EMS OVERRIDE, ETC.)LUMP SUM1$ 8 00,000$ 8 00,000
STRIPING AND SIGNAGE
HIGH VISIBILITY CROSSWALKLF100$ 100$ 10,000
PAVEMENT MARKINGSLUMP SUM1$ 10,000$ 10,000
HARDSCAPE
FENCESLF30$ 100$ 3,000
GATESEA2$ 3,000$ 6,000
REMOVABLE BOLLARDSEA4$ 2,000$ 8,000
OTHER
ENVIRONMENTAL PROTECTION (~2% CONSTRUCTION COSTS)LUMP SUM1$ 21,000$ 21,000
COORDINATION WITH EBRPDLUMP SUM1$ 1 00,000$ 1 00,000
GRAND TOTAL
2024 CONSTRUCTION COST$ 1,122,900
2030 TOTAL COST WITH GENERAL COST FACTORS (3)$ 2,557,488

RICHMOND PARKWAY TRANSPORTATION PLAN

Assumptions

  1. Trail section is 3" asphalt over 12" aggregate base.
  2. See General Cost Factors below.

General Cost Factors Mobilization, Demobilization, Environmental Protection, Traffic Control 1.20 Engineering, Design, and Construction Management 1.20 Inflation 1.22 Contingency 1.30 TOTAL - Combined Cost Factor 2.28

  1. Road section is 4,600 sf of 3" mill and overlay, plus 500 sf of new roadway section, which is 8" asphalt over 23" aggregate base.

Strategy WB-2

Original PDF, page 9

STRATEGY DG - 1 -- SIGNALS COSTS
Signal Strategy ComponentCost per IntersectionTotal Cost
Signal coordination$ 4,400$ 101,200
Connected battery backup system$ 13,750$ 123,750
Central signal management system$ 141,900$ 1,844,700
Signal hardware and software update$ 30,000$ 690,000
Emergecy vehicle preemption/transit signal priority$ 200,000
Adaptive traffic signal system$ 45,000$ 855,000
Connected Vehicle Roadside Unit$ 5,000$ 115,000
Subtotal - hardware and software$ 3,929,650
Design (15%)$ 589,448
Construction Management (10%)$ 392,965
Contingency (15%)$ 589,448
Grand Total (2024 Estimate)$ 5,501,510

STRATEGY DG - 1 -- SIGNALS COSTS

Strategy DG-1

Appendix F: Priority Strategy Cost Estimates |

RICHMOND PARKWAY TRANSPORTATION PLAN

Strategy M-1 - Pavement

Maintenance Cost Notes:

1) The cost table attached shows the maintenance treatment and costs both in 2024 and 2030 (2030 based on

when this project may actually be constructed) and assumes a 4% inflation rate.

2) The treatments shown are based on the projected 2030 pavement condition index (PCI) with an assumed

deterioration of 3 PCI points per year.

Year StreetID Street Name SectionID From To RPKYEB RICHMOND PKWY EB N/O CASTRO N/O REDWOOD RPKYEB RICHMOND PKWY EB N/O REDWOOD N/O MILLS RPKYEB RICHMOND PKWY EB N/O MILLS N/O GENERAL CHEMICAL ENTR RPKYEB RICHMOND PKWY EB N/O GENERAL CHEMICAL ENTR N/O HENSLEY RPKYEB RICHMOND PKWY EB N/O HENSLEY 2,277' @ CASTRO MERGE RPKYEB RICHMOND PKWY EB 2,277' @ CASTRO MERGE N/O GERTRUDE RPKYEB RICHMOND PKWY EB CITY LIMIT @ 1400' W/O GOODRICK AVE W/O GOODRICK AVE RPKYEB RICHMOND PKWY EB W/O GOODRICK W/O PKWY BRIDGE RPKYEB RICHMOND PKWY EB W/O PKWY BRIDGE E/O PKWY BRIDGE RPKYEB RICHMOND PKWY EB E/O PKWY BRIDGE S/O HILLTOP RPKYEB RICHMOND PKWY EB S/O HILLTOP S/O ATLAS RPKYEB RICHMOND PKWY EB S/O ATLAS W/O SAN PABLO RPKYEB RICHMOND PKWY EB W/O SAN PABLO WIDTH CHANGE (630' E/O SAN PABLO) RPKYEB RICHMOND PKWY EB WIDTH CHANGE (630' E/O SAN PABLO) E/O LAKESIDE RPKYEB RICHMOND PKWY EB E/O LAKESIDE W/O BLUME RPKYWB RICHMOND PKWY WB E/O SIERRA RIDGE E/O LAKSIDE DRIVE RPKYWB RICHMOND PKWY WB E/O LAKESIDE DRIVE WIDTH CHANGE (630' E/O SAN PABLO) RPKYWB RICHMOND PKWY WB WIDTH CHANGE (630' E/O SAN PABLO) W/O SAN PABLO RPKYWB RICHMOND PKWY WB W/O SAN PABLO S/O ATLAS RPKYWB RICHMOND PKWY WB S/O ATLAS S/O HILLTOP RPKYWB RICHMOND PKWY WB S/O HILLTOP E/O PKWY BRIDGE RPKYWB RICHMOND PKWY WB E/O PKWY BRIDGE W/O PKWY BRIDGE RPKYWB RICHMOND PKWY WB W/O PKWY BRIDGE W/O GOODRICK RPKYWB RICHMOND PKWY WB W/O GOODRICK AVE CITY LIMIT @ 1500' W/O GOODRICK AVE RPKYWB RICHMOND PKWY WB N/O GERTRUDE 1,350' @ ROAD SPLIT RPKYWB RICHMOND PKWY WB 1,350' @ ROAD SPLIT N/O HENSLEY RPKYWB RICHMOND PKWY WB N/O HENSLEY END PCC RPKYWB RICHMOND PKWY WB END PCC PENNSYLVANIA RPKYWB RICHMOND PKWY WB N/O GENERAL CHEMICAL ENTR N/O MILLS RPKYWB RICHMOND PKWY WB N/O MILLS 400 N/O REDWOOD RPKYWB RICHMOND PKWY WB 400 N/O REDWOOD N/O REDWOOD RPKYWB RICHMOND PKWY WB N/O REDWOOD N/O CASTRO GARRNB RICHMOND PKWY EB W OHIO MACDONALD GARRNB RICHMOND PKWY EB MACDONALD BARRETT GARRNB RICHMOND PKWY EB S/O BARRETT N/O PENNSYLVANIA / COP GARRSB RICHMOND PKWY WB N/O PENNSYLVANIA S/O BARRETT GARRSB RICHMOND PKWY WB BARRETT N/O MACDONALD GARRSB RICHMOND PKWY WB MACDONALD W OHIO

Original PDF, page 11

Area (SY) Current PCI 2030 PCI Treatment PCI After Treatment Unit Cost ($/SY) 2024 Cost Unit Cost ($/SY) 2030 Cost 2,951 THIN OVERLAY W/DIGOUTS $ 55.00 $ 162,000 $ 70.00 $ 207,000 6,490 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 594,000 $ 116.00 $ 753,000 12,280 RECONSTRUCT SURFACE (AC) $ 148.00 $ 1,817,000 $ 187.00 $ 2,296,000 7,957 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 728,000 $ 116.00 $ 923,000 8,594 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 786,000 $ 116.00 $ 997,000 6,773 RECONSTRUCT SURFACE (AC) $ 148.00 $ 1,002,000 $ 187.00 $ 1,267,000 5,444 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 498,000 $ 116.00 $ 632,000 8,089 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 740,000 $ 116.00 $ 938,000 9,396 Do Nonthing - PCC $

  • $ - $

28,722 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 2,628,000 $ 116.00 $ 3,332,000 9,778 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 895,000 $ 116.00 $ 1,134,000 7,233 RECONSTRUCT SURFACE (AC) $ 148.00 $ 1,070,000 $ 187.00 $ 1,353,000 2,660 SLURRY SEAL $ 3.50 $ 9,000 $ 4.50 $ 12,000 2,418 SLURRY SEAL $ 3.50 $ 8,000 $ 4.50 $ 11,000 17,991 THIN OVERLAY W/DIGOUTS $ 55.00 $ 990,000 $ 70.00 $ 1,259,000 10,550 THIN OVERLAY W/DIGOUTS $ 55.00 $ 580,000 $ 70.00 $ 739,000 2,342 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 214,000 $ 116.00 $ 272,000 4,340 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 397,000 $ 116.00 $ 503,000 7,233 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 662,000 $ 116.00 $ 839,000 8,800 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 805,000 $ 116.00 $ 1,021,000 24,288 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 2,222,000 $ 116.00 $ 2,817,000 9,396 Do Nonthing - PCC $

  • $ - $

8,089 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 740,000 $ 116.00 $ 938,000 5,833 RECONSTRUCT SURFACE (AC) $ 148.00 $ 863,000 $ 187.00 $ 1,091,000 6,300 SLURRY SEAL $ 3.50 $ 22,000 $ 4.50 $ 28,000 8,178 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 748,000 $ 116.00 $ 949,000 3,025 THIN OVERLAY W/DIGOUTS $ 55.00 $ 166,000 $ 70.00 $ 212,000 2,383 SLURRY SEAL $ 3.50 $ 8,000 $ 4.50 $ 11,000 11,169 RECONSTRUCT SURFACE (AC) $ 148.00 $ 1,653,000 $ 187.00 $ 2,089,000 5,067 RECONSTRUCT SURFACE (AC) $ 148.00 $ 750,000 $ 187.00 $ 948,000 3,300 RECONSTRUCT SURFACE (AC) $ 148.00 $ 488,000 $ 187.00 $ 617,000 3,504 RECONSTRUCT SURFACE (AC) $ 148.00 $ 519,000 $ 187.00 $ 655,000 8,462 THIN OVERLAY W/DIGOUTS $ 55.00 $ 465,000 $ 70.00 $ 592,000 3,911 THIN OVERLAY W/DIGOUTS $ 55.00 $ 215,000 $ 70.00 $ 274,000 7,076 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 647,000 $ 116.00 $ 821,000 7,076 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 647,000 $ 116.00 $ 821,000 3,911 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 358,000 $ 116.00 $ 454,000 8,462 THICK MILL AND OVERLAY W/DIGOUTS $ 91.50 $ 774,000 $ 116.00 $ 982,000 2024 Total 25,870,000 $ 2030 Total 32,787,000 $

3) Total costs include the section of Castro Street which was

the former Richmond Parkway and is labeled as part of the

Richmond Parkway in the City’s StreetSaver database. The

sections of Castro are at the end of the spreadsheet and are

separated by a darker line. If you wanted to take out these

sections from the 2030 costs would be about $4 million less.

Appendix F: Priority Strategy Cost Estimates |

Strategy M-1 - Pavement (Cont.)

Original PDF, page 12

STRATEGY M-1 -- MAINTENANCE (GENERAL)
Public Works Division Annual Cost
Street sweepingStreets Maintenance Division$160,431.84
Weed abatement, removal of illegal dumping, graffiti abatement, encampments (West Ohio to Giant Road)Abatement Division, Parkway$102,831.00
Weed abatement, removal of illegal dumping, encampments (Castro – Hensley to Pt. Richmond, Parkway – Giant Road to HWY I-80, Parkway – West Ohio to Pt. Richmond).Abatement Division, Parkway$219,792.40
GRAND TOTAL (2024 Estimate)$483,055.24

RICHMOND PARKWAY TRANSPORTATION PLAN

STRATEGY M-1 -- MAINTENANCE (GENERAL)

Strategy M-1 - General

STRATEGY T-1 - TRANSIT STRATEGY (Bus/Walking Improvements)
UNITQUANTITYUNIT COSTTOTAL COST
STRUCTURAL - RETAINING STRUCTURES
RETAINING WALLSLF250$ 600$ 150,000
NEW PAVEMENT - SHARED USE PATH
GRADINGCY370$ 8 0$ 2 9,600
HOT MIX ASPHALTTON40$ 170$ 6,800
AGGREGATE BASETON150$ 100$ 1 5,000
CONCRETE
CONCRETE (SIDEWALKS, CURB & GUTTER, CURB RAMPS, MEDIANS/PED ISLANDS, MEDIAN NOSES)SF2800$ 4 0$ 112,000
CONCRETE BUS PADSF1500$ 6 0$ 9 0,000
CURB RAMPS (EACH, EXTRA COSTS, FORMWORK, DWS)EA2$ 5,000$ 1 0,000
STRIPING AND SIGNAGE
PAVEMENT MARKINGS AND SIGNAGELUMP SUM1$ 40,000$ 4 0,000
OTHER
DEMOLITION (GENERAL)SF6600$ 1 0$ 6 6,000
BUS SHELTERS, BENCHES, ETC.LUMP SUM1$ 50,000$ 5 0,000
GRAND TOTAL
2024 CONSTRUCTION COST$ 569,400
2030 TOTAL COST WITH GENERAL COST FACTORS (3)$ 1,296,851
STRATEGY T-1 - TRANSIT STRATEGY (Bike lockers)
BIKE LOCKER PRODUCTS & SERVICESUNITQUANTITYUNIT COSTTOTAL COST
EQUIPMENT ACCESS HUB EQUIPMENT AND SERVICE DELIVERY INSTALLATION ANNUAL SERVICE AND OPERATIONS AGREEMENT4 2 1 7 5$ 9,880 $ 1,995 $ 1,000 $ 375 $ 840$ 3 9,520 $ 3,990 $ 1,000 $ 2,625 $ 4,200
LOCKER SPACE YEAR
SUBTOTAL$ 5 1,335
TAX$ 4,117
2024 BIKE LOCKER INSTALLATION COST$ 5 5,452

General Cost Factors Mobilization, Demobilization, Environmental Protection, Traffic Control 1.20 Engineering, Design, and Construction Management 1.20 Inflation 1.22 1.30 Contingency TOTAL - Combined Cost Factor 2.28 Assumptions

  1. See General Cost Factors below.
  2. Trail section is 3" asphalt over 12" aggregate base.
  3. Demolition (General) includes work to clear the site and remove roadway material and existing concrete improvements.
  4. Assume the retaining structures will be less than 4' tall.

1,352,303 $ TOTAL COST FOR STRATEGY T-1 - TRANSIT STRATEGY

Strategy T-1

Appendix F: Priority Strategy Cost Estimates |